File #: 311-15    Version: 1 Name:
Type: Resolution Status: Passed
File created: 5/13/2015 In control: City Council
On agenda: 5/12/2015 Final action: 5/12/2015
Title: Resolve relative to the completion of roadwork associated with water main replacement.

Title

Resolve relative to the completion of roadwork associated with water main replacement.

 

Body

 

Resolved: That it is the sense of the City Council that the Mayor authorize the attached Road Plan Proposal for the continuation of the roadwork associated with water main replacement, which also includes a plan for the allocation of Chapter 90 funds, per the updated schedule contained in the Mayor’s communication dated April 28, 2015.

 

Road Plan Proposal

Remaining Costs

10 Streets (page 1)                                                                $1,490,000.00                                                                                                          

 

Estimated Costs to complete

8 Streets in 2015 

already prepped (p2)                                           $1,600,200.00                                                                                                          

 

Estimated Costs to design

9 Streets already

surveyed for 2016 (p4)                                           $   80,850.00                                                                                                          

 

Estimated Costs to Survey

and Design 24 Streets (p5)                                           $  281,700.00                                                                                                          

 

Estimated Cost to Survey and

Design Remaining Streets (p6)                      $  265,440.00                                                                                                          

TOTAL:                                                                                    $3,718,190.00                                                                                                          

Amounts Owed for

prior contracts                                                                $  557,300.00                                                                                                          

  

Total Needed to be ready

to complete all streets by

EOY 2016                                                                                     $4,275,490.00                                                                                                          

                                                                                                                                                                        

 

Water and Sewer Enterprise

Fund Reserves                                                                $1,400,000.00                                                                                                          

Remaining Bond Funding                                           $1,700,000.00                                                                                                          

Chapter 90 Funding 2015                                           $1,175,490.00                                                                                                          

Suggested method of Funding                      $4,275,490.00                                                                                                          

                                                                                                                                                                        

                                                                                                                                                                        

Remaining Chapter 90 Funding divided equally among the Wards by Dollars: $800,000.00

(Each Ward Councillor would decide where the 100K was to be spent. 

 Each Ward is provided with $100,000 in Chapter 90 funds)                                                                                                                                                   

                                                                                                                                                                        

Chapter 90 Funds used                                                                $1,975,490.00                                                                                                          

Total Chapter 90 Funds Available                                           $2,400,000.00                                                                                                          

Remaining Chapter 90 Funds

determined by Mayor                                                                $424,510.00                                                                                                          

                                                                                                                                                                        

                                                                                                                                                                        

Further Mayor sends down $1,600,000 Bond to continue program

($200,000 per Ward for ripping up streets. Each Ward Councillor would decide which streets from a list provided by Engineering.   At $300 per ft this will provide 666 Ft)