File #: 59-21    Version: 1 Name:
Type: Petition Status: Agenda Ready
File created: 2/4/2021 In control: City Council
On agenda: 2/16/2021 Final action: 2/16/2021
Title: Petition: National Grid, 1101 Turnpike Street, North Andover, MA Massachusetts Electric Company d/b/a National Grid of North Andover, Massachusetts, that it desires to construct a line of underground electric conduits, including the necessary sustaining and protecting fixtures, under and across the public way or ways hereinafter named. Plan # 29146213 Fairlawn Street - permission to excavate the public highways and to run and maintain underground electric conduits, together with such sustaining and protecting fixtures as it may find necessary for the transmission of electricity, said underground conduits to be located substantially in accordance with the plan herewith marked: Fairlawn St. - Malden - Massachusetts. The following are the streets and highways referred to: Plan # 29146213 Fairlawn St - National Grid to install beginning at a point approximately 40 feet west of the centerline of the intersection of Main St. and Fairlawn St. and continuing approximately 6060 feet in a west...
Sponsors: Paul Condon
Attachments: 1. Fairlawn Street

Title

Petition:  National Grid, 1101 Turnpike Street, North Andover, MA

Massachusetts Electric Company d/b/a National Grid of North Andover, Massachusetts, that it desires to construct a line of underground electric conduits, including the necessary sustaining and protecting fixtures, under and across the public way or ways hereinafter named.

Plan # 29146213 Fairlawn Street - permission to excavate the public highways and to run and maintain underground electric conduits, together with such sustaining and protecting fixtures as it may find necessary for the transmission of electricity, said underground conduits to be located substantially in accordance with the plan herewith marked:  Fairlawn St. - Malden - Massachusetts.

The following are the streets and highways referred to:

Plan # 29146213 Fairlawn St - National Grid to install beginning at a point approximately 40 feet west of the centerline of the intersection of Main St. and Fairlawn St. and continuing approximately 6060 feet in a west direction.  Install 1 new manhole, 606’ of conduit, and trenching west from the intersection of Fairlawn St. and Main St.