File #: 167-15    Version: 1 Name:
Type: Committee Report Status: Passed
File created: 3/3/2015 In control: City Council
On agenda: 3/3/2015 Final action: 3/3/2015
Title: Committee Report: Ordinance (Paper #116 Amending Chapter 12 Section 800.3 to impose a moratorium on construction of residential dwelling units Committee recommends that this paper be referred to the Ordinance Committee and Planning Board with the following amendment: That everything after the enacting clause be stricken and the following inserted in place thereof: -by adding at the end of Section 800.3 the following: Notwithstanding the foregoing, no special permit, variance, site plan approval or building permit shall be issued for construction or creation of any residential dwelling unit, commencing on the first date of publication of this ordinance amendment and ending one year from the date of final enactment of this amendment; provided that this provision shall not apply to any application for or special permit, site plan approval, variance or building permit granted on or before the first publication of this ordinance amendment; and provided further that this provision shal...
Title
Committee Report: Ordinance (Paper #116 Amending Chapter 12 Section 800.3 to impose a moratorium on construction of residential dwelling units
Committee recommends that this paper be referred to the Ordinance Committee and Planning Board with the following amendment:
That everything after the enacting clause be stricken and the following inserted in place thereof:
-by adding at the end of Section 800.3 the following:
Notwithstanding the foregoing, no special permit, variance, site plan approval or building permit shall be issued for construction or creation of any residential dwelling unit, commencing on the first date of publication of this ordinance amendment and ending one year from the date of final enactment of this amendment;  provided that this provision shall not apply to any application for or special permit, site plan approval, variance or building permit granted on or before the first publication of this ordinance amendment; and provided further that this provision shall not apply to property located in the Central Business District, the Rowe's Quarry Reclamation District, or the Malden Center Revitalization Housing Development Incentive Zone, as established on December 9, 2014 .
The foregoing moratorium is imposed to allow the City time to undertake studies of the adequacy of the City's infrastructure, the scope of said studies to be determined during the public hearing process, and to consider amendments to the ordinance.