Title: Order: That the City Council adopt a schedule for completion of roadwork begun prior to December 2014. Ordered: That the City adopt the following schedule for completion of roadwork begun prior to December 2014: 1. Streets shall be completed in the order in which they were begun, based on information provided by the City Engineer; 2. Funds shall be transferred from reserve accounts in increments of $1,000,000 for completion of each section of work; 3. No additional funds shall be transferred from the reserve account until work approved for the previous section is 75% complete and the City Engineer has certified that the remaining 25% can be completed with the funds allocated.
Sponsors: Neil C. Kinnon, James M. Nestor
Title
Order: That the City Council adopt a schedule for completion of roadwork begun prior to December 2014.
Ordered: That the City adopt the following schedule for completion of roadwork begun prior to December 2014:
1.      Streets shall be completed in the order in which they were begun, based on information provided by the City Engineer;
2.      Funds shall be transferred from reserve accounts in increments of $1,000,000 for completion of each section of work;
3.      No additional funds shall be transferred from the reserve account until work approved for the previous section is 75% complete and the City Engineer has certified that the remaining 25% can be completed with the funds allocated.