84-25
| 1 | | | Committee Minutes | Minutes of December 10, 2024 to be approved. | tabled | Pass |
Action details
|
Not available
|
68-25
| 1 | | | Order | Order: That One Million Four Hundred Fifty Thousand Dollars ($1,450,000) is re-appropriated to pay costs of revitalization of Devir Park in the amount of $450,000 and the River Works park in the amount of $1,000,000, and for the payment of all costs incidental and related thereto, and that to meet this appropriation, $1,450,000 shall be re-appropriated from a portion of the amount borrowed on August 2, 2023 under the Loan Order passed by the City Council on June 11, 2019 to pay costs of Roosevelt Park revitalization, which project is abandoned and no liability remains, in accordance with G. L. c. 44 s. 20. | recommended favorably | Pass |
Action details
|
Not available
|
69-25
| 1 | | | Order | Order: That the appropriation enumerated below, being in the amount of $319,596 be appropriated from the Community Preservation Act Fund for the following project: Devir Park Revitalization Phase II:
Open Space Reserve $94,000
Budgeted Reserve $225,596
Total Appropriation= $319,596 | recommended favorably | Pass |
Action details
|
Not available
|
70-25
| 1 | | | Order | Order: That the appropriation enumerated below, being in the amount of $8,000 be appropriated from the Community Preservation Act Fund for the following project: Pearl Street Fire Station (176 Pearl Street) Envelope Assessment Project:
Historic Preservation Reserve $8,000
Total Appropriation $8,000 | recommended favorably | Pass |
Action details
|
Not available
|
71-25
| 1 | | | Order | Order: That the appropriation enumerated below, being in the amount of $8,000 be appropriated from the Community Preservation Act Fund for the following project: Oliver Street Fire Station (139 Oliver Street) Envelope Assessment Project:
Historic Preservation Reserve $8,000
Total Appropriation $8,000 | recommended favorably | Pass |
Action details
|
Not available
|
72-25
| 1 | | | Order | Order: That the appropriation enumerated below, being in the amount of $349,166.52 be appropriated from the Community Preservation Act Fund for the following project: Affordable Housing Trust Fund:
Community Housing Reserve $349,166.52
Total Appropriation= $349,166.52 | recommended favorably | Pass |
Action details
|
Not available
|
73-25
| 1 | | | Order | Order: That the appropriation enumerated below, being in the amount of $475,000 be appropriated from the Community Preservation Act Fund for the following project: Forest Dale Cemetery Wall Restoration Project:
Historic Preservation Reserve $278,000
Budgeted Reserve $197,000
Total Appropriation= $475,000 | recommended favorably | Pass |
Action details
|
Not available
|
74-25
| 1 | | | Order | Order: That the appropriation enumerated below, being in the amount of $14,500 be appropriated from the Community Preservation Act Fund for the following project provided that the appropriation is not to be used to repair or restore any item whose sole purpose is religious: St. Paul’s Parish Envelope Assessment Project:
Historic Preservation Reserve $14,500
Total Appropriation $14,500 | tabled | Pass |
Action details
|
Not available
|
75-25
| 1 | | | Order | Order: That the appropriation enumerated below, being in the amount of $40,000 be appropriated from the Community Preservation Act Fund for the following project: Housing Subsidy for Older Adults Project:
Budgeted Reserve $40,000
Total Appropriation= $40,000 | recommended favorably | Pass |
Action details
|
Not available
|
438-24
| 1 | | | Committee Minutes | Minutes of October 29, 2024 to be approved. | | |
Action details
|
Not available
|
|